Year: 2016
Comprehensive reconstruction to the U5-infopoint
Due to a comprehensive reconstruction, the U5-infopoint will be closed from January 1st to March 31st, 2017.
The newsletter of december is available now!
The new newsletter "Lückenschluss U5" is available now! In this edition we will focus on the design of our building fences as well as upcoming construction work on the U5 for the year 2017.
Unter den Linden: The underground station slowly reveals itself
For the last few months, work on Unter den Linden Station has gone on round the clock, slowly but surely revealing the transfer station in all its complexity and magnitude.
Museum Island: Modifications to the pedestrian walkway
In the past few weeks, there has been significant progress in construction of the Museum Island Underground Station. The final excavations have been closed and sealed, as well as the already-completed ice lance shafts. Now, builders can lay the lines ...
Open house at the Red City Hall Underground Station
Upon completion of its structural works, we cordially invite you to attend an open house at the Red City Hall Underground Station, to be held on 7 September 2016 from 2 p.m. to 8 p.m. at the construction site directly ...
Info-Flyer - June 2016
On our website you will find a current english flyer with general information on the gap closure of the U5.