A new era: Now the operations begin

Probebetrieb: IK-Zug auf Unter den Linden © A. Reetz-Graudenz

On 21st September, the entire new U5 construction project was handed over by BVG Projekt GmbH to the parent company BVG. This means that the new underground railway line is no longer a construction site, but officially enjoys the status of an operating facility. The last few weeks before commissioning are characterised by intensive preparations for the proper and safe operation of the underground railway from 4.12.2020. This includes above all comprehensive training of the employees who must familiarise themselves with the special features of the new line.