Danger! Hot! The rail welding © A. Reetz-Graudenz
April 9, 2019

Danger! Hot! The rail welding

The tunnel between the Rotes Rathaus underground station and the Museumsinsel underground station is hot: rail welding is in progress!

 

A shell is built on three levels © Reetz-Graudenz
March 1, 2017

A shell is built on three levels

The shell of underground station unter den Linden is in the final phase. In summer 2017 the expansion will begin.

 

Dismantling of the tunnels at underground station Museumsinsel © Reetz-Graudenz
Jan. 25, 2017

Dismantling of the tunnels at underground station Museumsinsel

Due to the completion of the shell construction at underground station Museuminsel, the dismantling of the tunnels has to be done.

 

Farewell to the construction workers of the shell at underground station Rotes Rathaus © Reetz-Graudenz
Jan. 5, 2017

Farewell to the construction workers of the shell at underground station Rotes Rathaus

The shell of underground station Rotes Rathaus has been completed. The shell of underground station Rotes Rathaus is followed by building it up.

 

Unter den Linden: The underground station slowly reveals itself © Reetz-Graudenz
Nov. 2, 2016

Unter den Linden: The underground station slowly reveals itself

For the last few months, work on Unter den Linden Station has gone on round the clock, slowly but surely revealing the transfer station in all its complexity and magnitude.

 

Museum Island: Modifications to the pedestrian walkway © Reetz-Graudenz
Oct. 20, 2016

Museum Island: Modifications to the pedestrian walkway

In the past few weeks, there has been significant progress in construction of the Museum Island Underground Station. The final excavations have been closed and sealed, as well as the already-completed ice lance shafts. Now, builders can lay the lines ...

 

Tags

Alex Tunnel Alex tunnel Alex-Tunnel Alexanderplatz BVG BVG Projekt GmbH Ballast Bank wall Braille Conduit Corona Demolition Diaphragm wall Dismantling Diver Electricity Fangedamm Foam glass gravel Friedrichstraße Gas Info-Flyer InfoTour Lighting Marx-Engels-Forum Museum Island Museumsinsel Pipes Rabitzdecke Rathausstraße Red City Hall Rotes Rathaus Schinkel blue Spreekanal Surface Tunnel U5 UdL Unter den Linden Wire saw accessibility back track wall ballast bench breakthrough building site calotte christmas cofferdam concreting conductor rail construction fence construction site cooperation december deconstruction delivery dismantling electrical elevator emergency telephone enclosures entrance area entrances escalator escalators exits extension finishing finishing works fire protection floor plates foam glass gravel gap closure granite guide system icing illustrated book info wagon infopoint infowaggon inner shell lamps lettering lifts lightening lights march mining tunnelling museum island museumsinsel new exhibition newsletter open house operations pipeline construction platform rabitz ceiling rail road track construction rail welding rear track wall rear track walls rotes rathaus schinkel sea of lights seating senate chancellery shell side galleries smoke extraction flaps special underground engineering stairs starry sky starting shaft structural work substructure subway surface surface restoration terrazzo test test run thawing topping-out ceremony tour track change track changing system track construction track switch area tracks tubbings tunnel tunnel walls u5 underconstruction underground underground station underground station Rotes Rathaus underground station museumsinsel underground station under den linden unter den linden vacuum cleaner video virtual reality wall plates work train

Archive zum Bautagebuch

This website uses cookies to enable certain functions and an user-oriented and smooth navigation. If you continue, you agree with the usage of cookies.